Slope stability in project is important and complicated problem. In fact, slope especially embankment often instability by many reasons such as foundation soil properties, lateral load, groundwater movement, … Therefore, it should to be use intergrated methods for reinforced and stable this object. This paper present intergrated methods of groundwater drainage, filling pile and soil mixing pile for reinforced embankment contruction works Z751/TCKT, Z756/BCCB factories in Long Binh ward, Bien Hoa city, Dong Nai province belong to 45 Project Management Unit - Department of Defense.